BAC AWARDS MARCH 2024 |
|
|
|
Tender/ Contract No. |
Date Awarded |
Description |
Company awarded the contract |
Tender Amount |
BAC - FRIDAY, 1 MARCH 2024 |
|
|
8/2/26/2023-2024P |
BAC, 1 March 2024 |
Formalization of contractor appointment: Refurbishment of Koonap River (Adelaide) Canal: Tender No. 8/2/26/2023-2024P, by an amount of R31 361 438.61 [Thirty-one million, Three hundred and sixty-one thousand, Four hundred and thirty-eight rand, sixty-one cents] including 10% Contingencies, 7.5% escalation and 15% VAT as per the Tendered Rates for the duration of 18 months. |
Messrs Tyeks Plant Hire and Construction |
R31 361 438.61 |
8/2/27/2023-2024P |
BAC, 1 March 2024 |
Formalization of contractor appointment: for the Stutterheim Sewer Pipe Replacement Program, Contract No. 8/2/27/2023-2024P, at an amount of R5 834 340.39 [Five Million, Eight Hundred and Thirty-Four Thousand, Three Hundred and Forty Rand, Thirty-Nine Cents] including 10% Contingencies, 10% escalation and 15% VAT as per the Tendered Rates for the duration of 9 months. |
Messrs Gqobo Investments cc |
R5 834 340.39 |
8/2/131/2020-2021C |
BAC, 1 March 2024 |
Approval for the replacement of HP EliteBook 650 G9, i7 1255U to the new HP EliteBook 650 G10, i7 1355U model [with a price difference of R355.00 from R25 625.00 to R25 980.00] in the term tender for IT equipment with Messrs Allied Business Solutions, Contract No. 8/2/131/2020-2021C ending 31st May 2025 |
Messrs Allied Business Solutions |
R355.00 |
BAC - WEDNESDAY, 13 MARCH AND THURSDAY, 14 MARCH 2024 |
8/2/54/2022-2023P |
BAC, 13& 14 March 2024 |
Revision of appointment: It is recommended that the appointment of Merss GG&G Consulting Engineers (Pty) Ltd for Elliotdale Wastewater Treatment Works: Contract no. 8/2/54/2022-2023P, be revised from the current appointed amount of R1 497 926.69 by an amount of R9 595 726.72 to the amount of R11 093 653.41 [Eleven million and ninety-three thousand, six hundred and fifty-three rands and forty-one cents] inclusive of VAT and disbursements. |
Merss GG&G Consulting Engineers (Pty) Ltd |
R11 093 653.41 |
8/2/90/2022-2023CP |
BAC, 13& 14 March 2024 |
Formalization of appointment: It is recommended that the appointment of Messrs Sontinga Consulting for the provision of consulting engineering services for the Ngqamakhwe Regional Water Supply Phase 3 project, Contract No. 8/2/90/2022-2023CP be formalized by an amount of R31 279 062.60 [Thirty-one million, Two hundred and seventy-nine thousand, sixty-two rands and sixty cents] inclusive of VAT and disbursements. |
Messrs Sontinga Consulting |
R31 279 062.60 |
BAC - THURSDAY, 28 MARCH 2024 |
8/2/119/2022-2023P |
BAC, 28 March 2024 |
Resolved to recommend to MM: It is recommended that a request is made to issue an addendum to revise the appointment amount to fully cover the scope of the project: Upgrading of Water Storage and Reticulation to accommodate future Development In Dutywa: Contract No. 8/2/119/2022-2023P. The Contractor’s current appointment, Messrs Simunye Developers’ amount is R25 471 523.56 and needs to be revised by R56 083 518.36 [Fifty-six million, Eighty- three thousand, five hundred and eighteen rands and thirty-six cents] to R81 555 041.92 [Eighty-one million, Five hundred and fifty-five thousand, forty-one rands and ninety-two cents] which is the initial appointment amount, due to funding availability. The revised amount is inclusive of 10% contingencies and 15% VAT for the completion of the project. |
Messrs Simunye Developers |
R81 555 041.92 |
8/2/59/2022-2023P |
BAC, 28 March 2024 |
Resolved to recommend to MM: Messrs Gilgal Global Africa (Pty) Ltd's appointment for the Upgrade of water storage and reticulation to accommodate future development in Dutywa (MIG Funded Phases 1,2,3,4&5) and the expansion of Dutywa supply (WSIG funded Phase 2) be revised from the current appointed amount of R10 135 063.41 by an amount of R24 943 537.83 [Twenty-four million Nine hundred and forty-three thousand, five hundred and thirty-seven rands and eighty-three cents] to R35 078 601.24 [Thirty-five million, seventy-eight thousand, six hundred and one rands and twenty-four cents] including VAT and disbursements, as approved by MIG. |
Messrs Gilgal Global Africa (Pty) Ltd |
R35 078 601.24 |
8/2/15/2023-2024C |
BAC, 28 March 2024 |
Extension of Scope: To extend the scope of works for Messrs Izwelethu Cemforce: Contract No. 8/2/15/2023-2024C to include construction of VIP toilets by Izwelethu Cemforce at an additional cost of R6600.00 excl. VAT per unit structure to cover construction/installation and management costs. |
Messrs Izwelethu Cemforce |
R6 600.00 |
|
|
|
|
|